← Retrospect libraryFREE READING EDITION

Science & engineering

Hydrokinetic Barge: Concept Sheet

Text edition. For original formatting, figures, and attachments, request the file by email from the library.

Prepared by

A companion engineering concept for a pilot barge module. Concept only; not a construction or permit package.

Email me the original file

Baton Rouge Hydrokinetic Barge ModuleEngineering Concept Sheet

Phase 1 Prototype | Concept-level package for engineering screening, investor discussion, and feasibility scoping

Status: Concept only — not for construction, procurement, navigation approval, or permit submittal

Recommended hull120 ft × 50 ft × 8 ft inland equipment/spud bargeDesign envelopeOutside maintained navigation corridor; retractable storm mode; armored shore export cable
Turbine package2 × 4.5 m variable-speed axial-flow rotors on retractable frame
Module output~110–135 kW at ~2.8–3.0 m/s current
Primary restraint4-point mooring to engineered pile/dolphin anchor groups

1. Basis of Design

Design intent is a single pilot-scale hydrokinetic barge module for deployment in the Baton Rouge reach of the Mississippi River, outside the maintained deep-draft navigation channel and outside critical levee and revetment conflict zones.

The concept uses a heavy inland equipment/spud barge as a support platform, a retractable steel turbine carriage carrying two submerged rotors, and a permanent 4-point mooring system with upstream load bias. Spuds are included for positioning and maintenance support only.

All values in this package are conceptual first-pass engineering values. Final design requires hydrodynamic surveying, geotechnical borings, bathymetry, navigation review, utility interconnection study, environmental review, and stamped structural and marine analyses.

2. General Arrangement

Top view

Figure 1. Top view with conceptual dimensions, turbine well, spuds, and 4-point mooring arrangement.

Side view

Figure 2. Side view showing hull, retractable twin-rotor carriage, export cable, and anchor dolphin concept.

Anchor / mooring layout

Figure 3. 4-point mooring concept with upstream primary groups and downstream stabilizing groups.

3. Principal Dimensions and Design Assumptions

ParameterValueUnitsNotes
Hull length overall120ftInland equipment/spud barge, raked upstream bow
Hull beam50ftSelected for stability, deck space, and twin-rotor packaging
Hull depth8ftTypical deck barge depth
Operating draft4.0–4.5ftTo be verified by final weight takeoff and freeboard calculation
Rotor quantity2eaHorizontal-axis hydrokinetic rotors
Rotor diameter4.5m~14.8 ft rotor diameter
Hub depth below normal surface18–22ftSite-tuned to balance output, clearance, and debris exposure
Bottom tip clearance8–12ftTo be verified with site bathymetry and scour envelope
Turbine well clear opening16 × 8ftConceptual internal opening for carriage and maintenance access
Spuds24 in × 45ftAuxiliary positioning only; not primary storm restraint
Anchor spread~160ftLateral distance between upstream groups
Fore/aft anchor spacing~70–90ftApproximate upstream-to-downstream group spacing
Export voltage13.8kVConceptual shore interconnect level

4. Preliminary Load Table

Loads below are first-pass conceptual values for screening the mooring and hull/frame arrangement. They are not final structural design loads.

Load caseCurrentEstimated loadUnitsComment
Twin-rotor thrust~2.8 m/s~100kNCombined thrust from both 4.5 m rotors
Twin-rotor thrust~3.0 m/s~115kNUpper normal operating band
Hull drag~2.8–3.0 m/s~75kNBarge aligned to current
Frame, appendages, misc. drag~2.8–3.0 m/s~30–50kNCarriage, cabling, miscellaneous components
Total service mooring load~2.8–3.0 m/s~205–240kNNormal operating envelope
Extreme/event screening loadhigh water + debris + dynamic margin~450–550kNPreliminary system design envelope
Upstream anchor group target working loaddesign basis300–400kN eachPrimary restraint capacity target
Downstream anchor group target working loaddesign basis150–200kN eachSecondary stability / yaw control
Total mooring system ultimate targetdesign basis>1,000kNTarget with redundancy and reserve

Key mechanical takeaway: this is a 0.1 MW-class module, not a 1 MW-class module. The engineering fight is survivability, restraint, access, and debris handling—not simply rotor power density.

5. Anchor and Mooring Concept

Recommended permanent restraint is a 4-point mooring to engineered anchor dolphins or pile groups rather than loose deadweight anchors. Upstream groups carry the dominant current load; downstream groups stabilize yaw, surge recovery, and fault tolerance.

Conceptual anchor group: two 30-inch OD steel pipe piles with 1-inch wall thickness, tied by a cap beam, with preliminary embedment screening in the 60–80 ft range below mudline. Final size and embedment depend on geotechnical borings, scour depth, and lateral analysis.

Mooring line concept: 1.5-inch wire rope or equivalent hybrid line upstream; 1.25-inch downstream. Add chafe protection, line monitoring, and replaceable connection hardware. Use two onboard 24-inch square spuds only for positioning, maintenance, and short hold periods.

6. Bill of Major Components

SystemMajor componentQtyConcept notes
Hull/platform120 ft × 50 ft × 8 ft inland equipment/spud barge1Raked upstream end, service deck, local crane pad, equipment zones
Positioning24 in × 45 ft spuds2Auxiliary hold only
Turbines4.5 m axial-flow hydrokinetic rotor assemblies2Variable speed, sealed nacelle, underwater bearings
Support frameRetractable steel carriage / portal frame1Raise/lower/lock positions for operation, inspection, storm mode
Debris managementFloating debris boom / deflector1 setAngled to steer drift away from rotor plane
MooringEngineered upstream anchor groups2Pile/dolphin groups with cap beam
MooringEngineered downstream anchor groups2Pile/dolphin groups with cap beam
Mooring hardwareWire rope / hybrid mooring lines, shackles, fairleads, instrumentation1 setOversized for river service
ElectricalUnderwater generators with drives / converters2480–690 V class at machine
ElectricalMain transformer and switchgear1 setBarge-mounted or shore mounted depending final arrangement
ElectricalArmored export cable to shore1 setBuried/protected at landing
ControlsSCADA, vibration monitoring, line tension monitoring1 setRemote alarms and performance tracking
SafetyNavigation lighting / marks, emergency retrieval gear1 setIntegrated with marine operations plan

7. Phase 1 Prototype Specification

Prototype objective: Prove survivability, power yield, maintenance access, and navigation compatibility through at least one full hydrologic cycle.

Nominal module rating: 110–135 kW expected at approximately 2.8–3.0 m/s current; design to capture operating data rather than advertise nameplate hero numbers.

Deployment mode: Single barge module located outside the maintained ship channel and outside critical bank/flood-control infrastructure conflict zones.

Storm strategy: Retract carriage to protected position and/or remove module from service during major storm or high-debris windows.

Target monitoring package: Rotor speed, generator power, vibration, bearing temperature, line tension, hull motions, current velocity, debris events, and scour observations.

Recommended engineering gates before fabrication: ADCP current survey, bathymetry, geotechnical borings, pile lateral design, hull stability review, mooring analysis, debris study, cable route study, and interconnection screening.

Recommended pilot duration: 12 months minimum, preferably covering one high-water season and one lower-water season.

Success criteria: No serious navigation conflict, acceptable maintenance burden, stable mooring performance, survivable debris events, and bankable net energy data.

8. Immediate Next-Step Work Package

1) Confirm a candidate river reach outside the navigation corridor and outside levee/revetment conflict zones.

2) Run ADCP transects to define the real velocity profile through the target operating depth band.

3) Collect borings and sediment data for pile design and scour protection.

4) Complete barge weight estimate, draft/freeboard check, and intact stability review for carriage-up and carriage-down conditions.

5) Run mooring analysis for normal operation, high water, asymmetric line loss, and debris strike scenarios.

6) Define export cable route and shore switchgear elevation above flood risk.

7) Build a utility/interconnection and permit map before advancing to procurement pricing.

Engineering caution: This concept package is intended to start real conversations with marine engineers, coastal/environmental engineers, fabricators, utilities, and investors. It is intentionally conservative on output and intentionally aggressive on survivability.

← Return to the library